Tuesday, July 30, 2013
Final Grading and Porch Stairs
The cabin was built on a grade that made it difficult to use the yard. We decided to bulldoze the yard to soften the grade and make it more usable. We ended up lowering the front yard by about five feet and pushing the excess to the edge. This created more level ground and the future home of a small barn or garage that will be added in the future.
Once we complete that, we started on the construction of the porch stairs. We didn't have time to install the railings but we'll get to that on another weekend.
Thursday, July 4, 2013
Exterior Stone
The exterior stone was installed on the cabin this past week. This will allow for the finish grade to be completed and the stairs to the deck to be set. We are planning on focusing on the exterior for now so that it will be completed by winter.
Subscribe to:
Posts (Atom)